Riyadh Metro Bridge Erection
Rapid erection of pre-cast concrete bridge segments across Riyadh's busy corridors.
April 2026 Riyadh

Project Overview
As part of the Riyadh Metro project development, BM Cranes managed the night-time lifting and alignment of heavy concrete viaduct segments. This required high-speed execution to prevent daytime traffic disruptions.
Key Challenges
01
Lifting within tight night-time window (12:00 AM to 5:00 AM).
02
Confined public roads with high overhead clearance hazards.
03
Handling asymmetric pre-cast concrete blocks.
Execution & Methodology
- Deployed dual 500-tonne mobile cranes for synchronous lift-and-swing operations.
- Engineered specialized spreader beams to handle concrete load distribution.
- Coordinated with Riyadh traffic police for temporary route diversions.
Results & Achievements
- Erected 18 major bridge spans with zero traffic delays.
- Achieved 100% compliance with RDA civil engineering standards.
- Awarded safety recognition shield by the BACS consortium.
Project Details
Location
Riyadh, Central Region, Saudi Arabia
Client
Riyadh Development Authority / BACS Consortium
Duration
20 Days
Equipment Used
Liebherr LTM 1500-8.1 (500T Mobile Crane) & LTM 1300
Date
April 2026