Yanbu Petrochemical Shutdown

Deploying a massive surge fleet of heavy cranes for a fast-track turnaround shutdown.

January 2026 Yanbu
Yanbu Petrochemical Shutdown

Project Overview

During a major annual turnaround in Yanbu, BM Cranes mobilized a comprehensive fleet of cranes and certified personnel to handle 24/7 turnaround maintenance and vessel replacements.

Key Challenges

01

Managing over 10 simultaneous lift zones safely.

02

Mobilizing and certifying 40+ operators and riggers.

03

Zero tolerance for schedule slippage as plant downtime costs millions daily.

Execution & Methodology

  • Established an on-site command center with a resident lift planner.
  • Pre-assembled rigging gear and certified slings in modular containers.
  • Implemented a two-shift 24/7 operator roster.

Results & Achievements

  • Successfully replaced 14 major heat exchangers and 2 reactor heads.
  • Completed all lifts 36 hours ahead of the target turnaround schedule.
  • Zero HSE incidents reported during peak high-intensity shutdown.

Project Details

Location
Yanbu, Western Province, Saudi Arabia
Client
SABIC Affiliate / Petrochemical Operator
Duration
28 Days
Equipment Used
6× 300T Mobile Cranes, 4× 160T mobile cranes, & auxiliary units
Date
January 2026